Working for you Pentecost 2019

construction works/projects
// 3 May 2019

In order to keep on offering quality services to their customers, CFL carry on with maintenance, modernisation and extension works on the Luxembourgish railway network. These railway infrastructure works require the closure of certain railway segments in order to permit that these can be performed safely and swiftly.

Line 10 (Luxembourg – Troisvierges – Gouvy

Closure of the section of the line between Ettelbruck and Troisvierges
– from Saturday 25th May to Sunday 2nd June 2019 included

Closure of the section of the line between Ettelbruck and Diekirch
– on the weekends of 25th and 26th of May 2019 & 1st and 2nd of June 2019

Line 60 (Luxembourg – Esch-sur-Alzette ‒ Pétange ‒ Rodange)

Closure of the section of the line between Esch-sur-Alzette and Rodange
– from Saturday 25th May 2019 until Sunday 2nd June 2019 included

Substitution measures
Substitution measures line 10 (Luxembourg – Troisvierges – Gouvy)
Substitution measures line 60 (Luxembourg – Esch-sur-Alzette ‒ Pétange ‒ Rodange)